DHIS2 MIS Amakomaya Upgrade Process
1. DHIS2 Release Cadence:
- DHIS2 releases major versions twice a year.
- The core team supports the three most recent versions (e.g., if 2.41 is the latest, 2.39-2.41 are supported).
- Importance: Stay on a supported version to ensure you receive security patches and updates.
- Please see the official DHIS2 roadmap
2. Upgrade Process:
- A full database backup is essential before any upgrade.
- If critical errors are encountered, the upgrade will be rolled back, and further steps will be discussed.
3. Testing:
- Test the new release with a copy of your production database in a non-production environment.
Critical Testing Areas:
4. Rollback Limitations:
- Rolling back to a previous DHIS2 version is not possible; instead, the database will be restored from the backup.
- Any data or structure changes made after the upgrade will be lost if rollback is needed.
5. Performance Expectations:
- As DHIS2 evolves, resource requirements increase.
- If the system performs poorly after an upgrade, consider upgrading the hosting plan.
6. Scheduling:
- After thorough testing, schedule the upgrade during business hours for minimal disruption.
By following these guidelines, the DHIS2 MIS Amakomaya upgrade process will be smoother, ensuring security, stability, and performance improvements in line with the latest version.